Simple Question about Lead Time Calculation

Hi,
I found in the documentation that Lead Time is calculated in days. Does it use 7 day weeks or is it work days? We have a 32 week lead time so there is a large difference between 7 vs 5 day weeks :slight_smile:
Thanks
Melissa

1 Like

From the Scheduling Technical Reference:

Days Out is a value you define on subcontract operations. It is the estimated number of working days during
which the operation’s part quantity is out of your manufacturing center for supplier work.
This value is used with the supplier calendar to determine actual dates during which the materials will be away
from your manufacturing center.

Sorry about that. I should be more specific :slight_smile: I am looking at the manufacturing lead time in the part master on the plant, planning tab. We are entering manually instead of calculating it.

It should be calendar days

1 Like