Materials Issued Qty consistently 4-5 times the Required Qty on one part

jobs
material
(Logan Albrecht) #1

Only one specific part is having this issue.
Every time this material is issued for the job, the issued qty is around 4.5 times the required qty.
I assume there is some multiplier or conversion that is happening that needs to be changed, but I have no idea where to look or how to go about that. I’ve only been working with E9 a few days.

Thanks for the help,
Logan

example

0 Likes

(Bruce Ordway) #2

I suspect it is the same amount but shown in different units?
e.g. a required qty of 1 in Gallons (Job UM), vs. an Issued qty of 4 in Quarts (Inv UM)?

If you look at the part tracker UOM List, does that give you any clues?
Or maybe the Part Transaction History tracker for that part number?

1 Like