Jobs with multiple operations

is this what you mean?

finished part A (is assembly 0 on the job) Sometimes we just have the
final assembly and packaging on this part.
.Assy1 Part B some materials and machine ops as a sub assembly to A which
is consumed by A
..Assy2 Part C some materials and machine ops as a sub assembly to B
which is consumed by B
.Assy3 Part D some materials and machine ops as a sub assembly to A which
is consumed by A

and so on. the (.)in front of the sub assembly shows it as a component of
the main part, and (..) shows it as a component to the subassembly it is
following.

Every assembly can be composed of other machined parts, they are sub
assemblies to it.
Example:
We have had plates we machine and then weld to 2 stand-offs. They each have
their own material, and operations. The welding is the subcontract op.
When this is finished, they are a completely new part number. Complete the
job/assemblies, and the costs roll up to the next level. The new part is
used as a component to a larger machine as well.

Rhonda

-----Original Message-----
From: sharma_nalini [mailto:sharma_nalini@...]
Sent: Friday, April 08, 2005 11:14 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Jobs with multiple operations




1.Does any one have example of how to Create Job/BOM with multiple
examples where master part no changes from A to B when send out to
subcontractor for something and then come back with different part no C.

Also how can we track inventory of parts like them.
HOw can we track Work in process.

2.Another example where we don't know how to create BOM is:

Master manufactured parts has multiple operations with no of others
components which are also manufactured at the facility.


I am sorry, if i am not clear enough.






Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
<http://groups.yahoo.com/group/vantage/files/.>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
<http://groups.yahoo.com/group/vantage/messages>
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
<http://groups.yahoo.com/group/vantage/links>



_____

Yahoo! Groups Links


* To visit your group on the web, go to:
http://groups.yahoo.com/group/vantage/
<http://groups.yahoo.com/group/vantage/>


* To unsubscribe from this group, send an email to:
vantage-unsubscribe@yahoogroups.com
<mailto:vantage-unsubscribe@yahoogroups.com?subject=Unsubscribe>


* Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service
<http://docs.yahoo.com/info/terms/> .




[Non-text portions of this message have been removed]
1.Does any one have example of how to Create Job/BOM with multiple
examples where master part no changes from A to B when send out to
subcontractor for something and then come back with different part no C.

Also how can we track inventory of parts like them.
HOw can we track Work in process.

2.Another example where we don't know how to create BOM is:

Master manufactured parts has multiple operations with no of others
components which are also manufactured at the facility.


I am sorry, if i am not clear enough.