Constrained Material

Vantage 8.03.410

Any ideas as to why the “Constrained Material” checkbox is grayed out in Part Maintenance?

Is the part a Non-Stock one by chance? I believe that a part must be a Stock item to have the Contrained Material be on…

Brad Boes
bradboes@boosterpconsulting.com
231-845-1090

Thanks Brad.

No, these are all “Purchased” and “Stock” parts. The “Constrained Material” box is grayed out on all of them, which is impacting my scheduling.

So, I just got off the phone with support and they tell me I need APS to utilize this feature, which I don’t.

So, my material has a 5 day lead-time, which is considered in my Purchase Suggestions, however my Job is not going to consider that lead-time and schedule to start my Job now.

WTH… Am I missing something?