Can you assign people to shift A
Then every 2 weeks or so change the hours in
Then in Job > Master File > Shift Master
Just a thought.
BW
-----Original Message-----
From: gfxltd2004 [mailto:rmacdonald@...]
Sent: Thursday, March 24, 2005 9:45 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Plant Shift Rotation
Hi All,
We rotate our plant shifts every two weeks, and in our old system we
had the ability to change the employee's shift's in a batch mode.
After a call to tech support, I was told that Vantage 6.1 does not
have the ability to automate this functionality.
Tech Support has attached my call to a previous enhancement request,
but my hope of this enhancement request happening in my lifetime is
low. Therefore, does anyone have a script or other automated method
for changing the shift of 150+ employee's every two weeks.
Thanks,
Rob MacDonald
Then every 2 weeks or so change the hours in
Then in Job > Master File > Shift Master
Just a thought.
BW
-----Original Message-----
From: gfxltd2004 [mailto:rmacdonald@...]
Sent: Thursday, March 24, 2005 9:45 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Plant Shift Rotation
Hi All,
We rotate our plant shifts every two weeks, and in our old system we
had the ability to change the employee's shift's in a batch mode.
After a call to tech support, I was told that Vantage 6.1 does not
have the ability to automate this functionality.
Tech Support has attached my call to a previous enhancement request,
but my hope of this enhancement request happening in my lifetime is
low. Therefore, does anyone have a script or other automated method
for changing the shift of 150+ employee's every two weeks.
Thanks,
Rob MacDonald