One Job manufactures two stocked items


(Richard) #1

I have a part A that is a Make to Stock item. When it is manufactured it also makes a second part B that also goes to stock. How does this get reflected in the BOM?

Part A consumes two raw materials Raw1 and Raw2. When the Manufacturing Job is completed both Part A and Part B are added to Inventory.

How does this get reflected in the Part A - BOM?


(Rye) #2

Have you tried coparts yet? It sounds like these are coparts.


(Richard) #3

Thanks - That is what I needed.


(Rye) #4

you’re welcome!