Error when reporting operation on a "late job"

e10

(KEVIN SOUTHER) #1

I have been getting a error occasionally when trying to report the operations, "specified argument out of range…).
When I look at the job it is late. If I remove it from the schedule, and then report the quantity… it reports fine.

What is causing this?


(Rye) #2

Hi Kevin,

Usually what I find has caused it is that someone has changed something within the job without removing the job from the schedule and re-scheduling it. There is normally something out of sync (change of resource, change of material, etc.).

Beth


(KEVIN SOUTHER) #3

Thanks, I’ll keep looking at those types of things.


(Rye) #4

The only way out of the error is to remove the job from the schedule and reschedule it.