Backflushing Lot Tracked Materials

Ive developed this through UD tables and service connect

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of scottyk537@...
Sent: Wednesday, October 09, 2013 3:16 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Backflushing Lot Tracked Materials



To the customization masters out there:

I'm wondering if any of you have successfully implemented a customization that allows you to backflush lot tracked materials.

I have a couple ideas:

Use a UD table to store a set of lot tracked materials for an operation. This would be the material queue. Then customize the report quantity screen to basically call the issue material BO.

I have not started to attempt this customization, but just wondering if there is a better approach.

Thanks,



Scott



[Non-text portions of this message have been removed]

To the
customization masters out there:

I’m wondering if any of you have successfully implemented
a customization that allows you to backflush lot tracked materials.

I have a couple ideas:

Use a UD table to store a set of lot tracked materials
for an operation. This would be the material queue. Then customize the report
quantity screen to basically call the issue material BO.

I have not started to attempt this customization, but
just wondering if there is a better approach.

Thanks,

 

Scott